質問 1:Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)
A. If the "Allow resource changes at project level" option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.
B. If the "Allow resource changes at project level" option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.
C. If the "Allow resource changes at project level" option is set to Yes for the RBS, the new resources are available automatically at project level.
D. If the "Allow resource changes at project level" option is set to No for the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 2:Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)
A. Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.
B. Labor Demand FTE is calculated as Project Allocation hours divided by Project FTE hours, if project duration is used as the basis for viewing labor demand.
C. Labor Demand FTE is calculated as Quarterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.
D. Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.
正解:C,D
解説: (Topexam メンバーにのみ表示されます)
質問 3:Your organization wants to capture the project details for work order labor and equipment resource transactions as part of a project-driven supply chain solution.
Which expenditure type class is recommended for the expenditure types that need to be defined for these type of transactions?
A. Usages
B. Work In Process
C. Inventory
D. Supplier Invoice
正解:B
解説: (Topexam メンバーにのみ表示されます)
質問 4:You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)
A. Exceptions
B. Expenditure Type
C. Workday Patterns
D. Accounting Calendar
E. Time Off
正解:A,C
解説: (Topexam メンバーにのみ表示されます)
質問 5:Which three file-based data imports are available for use in Oracle Project Portfolio Management Cloud?
A. Project Billing Events
B. Project Templates
C. Capital Rate Schedule
D. Project Tasks
E. Project Budgets
正解:A,D,E
解説: (Topexam メンバーにのみ表示されます)
質問 6:A consulting services company is currently working on a business transformation project for your client that spans over 10 months. The total contract amount is 250000 USD. They have generated a revenue of 25000 USD and an Invoice of 10000 USD at the end of the first period.
The accounting entry for revenue is:

and accounting entry for invoice is:

What will be the accounting entry when you reclassify the billing offset balances in the first period?
A. Dr Deferred Revenue 10000 -
Cr Unbilled Receivables 10000
B. Dr Accounts Receivables 10000 -
Cr Revenue 10000
C. Dr Accounts Receivables 10000 -
Cr Unbilled Receivables 10000
D. Dr Unbilled Receivables 10000 -
Cr Accounts Receivables 10000
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 7:Your client has decided to import time cards into Project Costing from Oracle Fusion Time and Labor. They have a requirement to make adjustments to time card entries whenever needed.
In which work area will the employees and contingent workers be able to modify their time cards?
A. Cost
B. Time
C. Both Time and Cost
D. Asset
正解:B
解説: (Topexam メンバーにのみ表示されます)
質問 8:Your customer accounts revenue based on, product class category. Because all your customer's projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category "Funding Source" and assign it to all projects. However, you notice that the accounting is still happening based on product class category. Identify the reason for this problem. (Choose the best answer.)
A. Product class category is not enabled for "available as accounting source".
B. Funding source class category is not enabled for "available as accounting source".
C. Funding source class category is assigned to all project types.
D. Funding source class category is enabled for "available as accounting source".
正解:B
解説: (Topexam メンバーにのみ表示されます)
質問 9:Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)
A. Current date is before the effective date of the resource, and you did not enable the "Include people with future-dated effective start dates" option during the search.
B. All new employees created as persons must have an active project role.
C. All new employees created as persons must have an active supervisor.
D. All new employees created as persons must have an active assignment.
E. All new employees created as persons must be assigned to a department.
正解:A,D,E
解説: (Topexam メンバーにのみ表示されます)
Oracle 1z0-1057-22 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Navigation, User, Personalization and Approvals
- Describe the Applications Security Console
|
トピック 2 | - Describe the components of Oracle Project Management Cloud
- Set up Project Financial Management Organizations
|
トピック 3 | - Configure Project Cross Charging and Transfer Pricing
- Explain the components available for integration
|
トピック 4 | - Configure and Manage Project Invoicing and Revenue
- Describe common project execution components
|
トピック 5 | - Set up Project Calendars and Periods
- Set up approval and notification tasks
- Project Management Overview
|
トピック 6 | - Configure Project Resource Management
- Configure Project Performance Reporting
|
参照:https://education.oracle.com/oracle-project-management-cloud-2022-implementation-professional/pexam_1Z0-1057-22
一年間の無料更新サービスを提供します
君が弊社のOracle 1z0-1057-22をご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたOracle 1z0-1057-22をお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のOracle 1z0-1057-22を持っていることを保証します。
弊社は無料Oracle 1z0-1057-22サンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料1z0-1057-22サンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこの1z0-1057-22問題集は自分に適するかどうか判断して購入を決めることができます。
1z0-1057-22試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社の1z0-1057-22問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
TopExamは君に1z0-1057-22の問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。
弊社は失敗したら全額で返金することを承諾します
我々は弊社の1z0-1057-22問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のOracle 1z0-1057-22を利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
弊社のOracle 1z0-1057-22を利用すれば試験に合格できます
弊社のOracle 1z0-1057-22は専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社は1z0-1057-22問題集の質問と答えが間違いないのを保証いたします。

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のOracle 1z0-1057-22を利用すれば、君は一回で試験に合格できます。