質問 1:
The following are the requirements identified as "critical":
REQ-SEL-001. The user shall be able to combine all the three products with all the four
durations to define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the
shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using
a credit voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using
the available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using
all the accepted credit cards (Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both
the "select" and "purchase" pages going back to the "browse" page (anonymous
navigation)
Moreover the following quality risk item has been identified as "critical":
QR-P1. The web customer portal might not be able to provide the expected response time
(less than 10 sec) for the purchase transactions under a load of up-to 1000 concurrent
users
Test analysis for system testing has just begun and the following test conditions have been
identifieD.
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
What is the MINIMUM number of test conditions that must be added to fulfill both the
EXCR1 and EXCR2 exit criteria?
K3 2 credits
A. 2
B. 3
C. 4
D. 1
正解:B

質問 2:
The main objectives the senior management team wants to achieve are:
- to reduce the costs associated with dynamic testing
- to use reviews to ensure that the project is on course for success and following the plan
- to use reviews as a well-documented and effective bug-removal activity following a formal
process with well-defined roles
- to determine the effectiveness of reviews in terms of phase containment
- to improve phase containment effectiveness
Which of the following answers would you expect to describe the best way to achieve these
objectives?
K4 3 credits
A. You should plan for formal exit-phase reviews at the end of each development and
testing phase, and plan for a process of gathering information from testing to perform an
analysis of the bugs found during testing to determine the phase in which they have been
introduced
B. You should plan for lightweight exit-phase reviews at the end of each development and
testing phase, and plan for a process of gathering information from testing to perform an
analysis aimed at identifying the larger cluster of defects
C. You should plan for formal exit-phase reviews at the end of each development and
testing phase, and plan for a process of gathering information from testing to perform an
analysis aimed at identifying the larger cluster of defects
D. You should plan for formal exit-phase reviews at the end of each development phase
and testing phase, and plan for a process of gathering information from testing to perform
an analysis of the bugs found during testing to determine the people responsible for those
bugs
正解:A

質問 3:
Consider the following list of statements about audits and management reviews:
I. Audits are usually more effective than management reviews at finding defects
II. Audits and management reviews have the same main goals, the only difference is
related to the roles and level of formality
III. A typical outcome of an audit includes observations and recommendations, corrective
actions and a pass/fail assessment
IV. An audit is not the appropriate mechanism to use at the code review in order to detect
defects prior to dynamic testing
Which of the following statements is true?
K2 1 credit
A. III. and IV. are true; I and II are false;
B. II. and III are true; I. and IV. are false;
C. I, III and IV are true; II. is false;
D. I. and III. are true; II. and IV. are false;
正解:A

質問 4:
Consider the following statements describing the importance of improving the test process:
I. Test process improvement is important because being focused only on the test process it
can provide recommendations to improve the test process itself, but it can't indicate or
suggest improvement to areas of the development process
II. Test process improvement is important because it is much more effective than software
process improvement to improve the quality of a software system
III. Test process improvement is important because several process improvement models
(STEP, TPI Next, TMMi) have been developed over the years
IV. Test process improvement is important because every organization, regardless of the
context, should always achieve the maximum level of maturity of testing described in the
test improvement models such as TMMi
Which of the following answers is correct?
K2 1 credit
A. I. and IV. are true; II. and III. are false
B. I., II., III. and IV are false
C. I., II. and III. are false; IV. is true
D. I., II. and III are true; IV. is false
正解:B

質問 5:
Consider a defect report and assume that a part of its lifecycle includes the following
states:
New: Is the initial state
WorkinG. Means that the developers are addressing the defect in order to produce a fix for
the defect Clarification: Means that the developers need more information from the tester to
address the defect and produce a fix for the defect and the tester is working to provide this
information to the developers Verification: Means that a fix for the defect has been
produced and the tester is running the adequate tests to verify whether the fix solves the
defect
CloseD. is the final state
Which of the following answers represents an invalid sequence of states that can't lead the
bug report to the "Closed" state?
K2 1 credit
A. New, Working, Verification, Working, Clarification, Working, Verification, Closed
B. New, Working, Verification, Closed
C. New, Working, Clarification, Working, Verification, Closed
D. New, Working, Verification, Working, Clarification, Working, Closed
正解:D

質問 6:
Which of the following would you expect to be most likely an example of a demotivating
factor for testers?
K2 1 credit
A. The management asks the testers to be kept informed about the intensity, quality and
results of testing
B. The testers are assessed on whether and how often they detect important and critical
failures
C. Test quality is measured by counting the number of customer/user reported problems.
D. The same regressions tests are manually executed by the same testers, for every
product release, without regression test tools
E. The testers' recommendations to improve the system or its testability are adopted by the
development team
正解:C,D

弊社は失敗したら全額で返金することを承諾します

我々は弊社のATM問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のISTQB ATMを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。

弊社は無料ISTQB ATMサンプルを提供します

お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料ATMサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのATM問題集は自分に適するかどうか判断して購入を決めることができます。

ATM試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。

弊社のISTQB ATMを利用すれば試験に合格できます

弊社のISTQB ATMは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はATM問題集の質問と答えが間違いないのを保証いたします。

ATM無料ダウンロード

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のISTQB ATMを利用すれば、君は一回で試験に合格できます。

TopExamは君にATMの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。

一年間の無料更新サービスを提供します

君が弊社のISTQB ATMをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたISTQB ATMをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のISTQB ATMを持っていることを保証します。

ISTQB ATM 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Maintain the validity of certifications already obtained
トピック 2
  • Extend the coverage of ISTQB® certifications to additional specific topics.
トピック 3
  • Maintain the focus on software testing

参照:http://www.istqb.org/certification-path-root/advanced-level/advanced-level-test-manager.html

安全的な支払方式を利用しています

Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のATM問題集は全部Credit Cardで支払われることができます。

領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。

ATM 関連試験
CTFL-2018-Deutsch - ISTQB Certified Tester Foundation Level 2018 (CTFL-2018 Deutsch Version)
CTFL-2018 - ISTQB Certified Tester Foundation Level 2018
ATM-Deutsch - ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] (ATM Deutsch Version)
連絡方法  
 [email protected] サポート

試用版をダウンロード

人気のベンダー
Adobe
Apple
Avaya
CheckPoint
Citrix
CIW
CompTIA
EC-COUNCIL
EXIN
FileMaker
IBM
Juniper
Lotus
Lpi
Network Appliance
OMG
Oracle
PMI
SNIA
Symantec
VMware
XML Master
Zend-Technologies
The Open Group
H3C
F5
3COM
BEA
Dell
ACI
すべてのベンダー
TopExam問題集を選ぶ理由は何でしょうか?
 品質保証TopExamは我々の専門家たちの努力によって、過去の試験のデータが分析されて、数年以来の研究を通して開発されて、多年の研究への整理で、的中率が高くて99%の通過率を保証することができます。
 一年間の無料アップデートTopExamは弊社の商品をご購入になったお客様に一年間の無料更新サービスを提供することができ、行き届いたアフターサービスを提供します。弊社は毎日更新の情況を検査していて、もし商品が更新されたら、お客様に最新版をお送りいたします。お客様はその一年でずっと最新版を持っているのを保証します。
 全額返金弊社の商品に自信を持っているから、失敗したら全額で返金することを保証します。弊社の商品でお客様は試験に合格できると信じていますとはいえ、不幸で試験に失敗する場合には、弊社はお客様の支払ったお金を全額で返金するのを承諾します。(全額返金)
 ご購入の前の試用TopExamは無料なサンプルを提供します。弊社の商品に疑問を持っているなら、無料サンプルを体験することができます。このサンプルの利用を通して、お客様は弊社の商品に自信を持って、安心で試験を準備することができます。