質問 1:The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:
A. Total float
B. Free float
C. Just-in-time scheduling
D. Remaining duration
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 2:Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)
A. ACWP/BCWP
B. ACWP/BCWS
C. BCWS/BCWP
D. BCWP/ACWP
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 3:A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.
A. milestone activities
B. constraints, resource leveling, and interruptible activities
C. activities with short durations
D. activities with lag
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 4:After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.
What is the schedule variance (SV)?
A. BCWS - BCWP = 100.000 - 105,000 = -5,000
B. ACWP - BCWS = 110.000 - 100,000 = 10,000
C. BCWS -ACWP = 100.000 - 110,000 - -10,000
D. BCWP - BCWS = 105.000 - 100.000 =- 5,000
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 5:You have been hired as the cost engineer for a mechanical contractor and have been provided the following information:

What is the schedule performance index (SPI)?
A. ACWP/BCWS= 110,000/100,000= 1.10
B. BCWS/BCWP= 100,000/105,000-0.95
C. BCWP/BCWS = 105,000/100,000- 1.05
D. BCWS/ACWP = 100,000/110,000 = 0.91
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 6:As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.
The following revenue and expense relationships are predicted:

If XYZ considers S550 per month the minimum acceptable net income, the number of units that will have to be sold is:
A. 65,500 units
B. 40,000 units
C. 60,000 units
D. 50,000 units
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 7:An owner advertised his villa for sale. An investor worked out an estimate on the basis mat the villa could be rented out for $1000 per month. Maintenance charges and other taxes are estimated to be $1,500 per year. The tenant has to pay all utility charges. The investor thinks that he can sell this villa for S100.000 alter 6 years. Assuming that the minimum acceptable rate of return is 12%. answer the following question.
The villa could be recommended for purchase at all of the below-mentioned prices except:
A. $94,500
B. $92.800
C. $90,5000
D. $93,500
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 8:An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
You have been asked to provide ETC information to management. Based on the following information, what is the ETC?
Original Budget = $9,000,000
Actuals to date = $3,513,000
Current estimate at completion = $10,613,000
Actuals for current month = $1,200,000
A. $9,000,000
B. $10,613,000
C. $5,487,000
D. $7,100,000
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 9:The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
Calculate the weighted average unit cost.
A. $47.63
B. $48.09
C. $46.13
D. $48.35
正解:A
解説: (Topexam メンバーにのみ表示されます)
弊社のAACE International CCPを利用すれば試験に合格できます
弊社のAACE International CCPは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はCCP問題集の質問と答えが間違いないのを保証いたします。

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のAACE International CCPを利用すれば、君は一回で試験に合格できます。
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のCCP問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
弊社は無料AACE International CCPサンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料CCPサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのCCP問題集は自分に適するかどうか判断して購入を決めることができます。
CCP試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
TopExamは君にCCPの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。
弊社は失敗したら全額で返金することを承諾します
我々は弊社のCCP問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のAACE International CCPを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
AACE International CCP 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Cost Estimating: This section focuses on diverse estimating methodologies, techniques, cost evaluation, and effective management of cost data to ensure precise project estimates.
|
トピック 2 | - Cost Control: In this section, candidates are tested for skills related to budgeting, forecasting, cost management techniques like EVM, handling scope changes, and evaluating cost-related risks and performance metrics.
|
トピック 3 | - Planning and Scheduling: This section covers project planning, resource management, scheduling strategies, and approaches for monitoring, controlling, and assessing schedule risks.
|
参照:https://web.aacei.org/certification/certification-information/certifications-offered/professional-certifications/ccp-details
一年間の無料更新サービスを提供します
君が弊社のAACE International CCPをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたAACE International CCPをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のAACE International CCPを持っていることを保証します。