質問 1:Which is a reason for 'blending and weaving' PRINCE2 with agile at all levels within a project?
A. To adjust a 'command and control' culture for product delivery.
B. Projects should be established with the intention of NOT delivering everything.
C. To allow teams to self-organize whilst staying in control.
D. PRINCE2 Agile is NOT a substitute for PRINCE2.
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 2:Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
When contributing to the development of the communication management approach, the Marketing Team felt that the only applicable agile technique to be included in the approach was the use of daily stand-ups.
Which reason BEST explains whether this is a suitable entry for 'tools and techniques' in the communication management approach?
A. It is suitable because the marketing products are already rich in communication.
B. It is suitable because the marketing products do NOT suit the use of other agile techniques.
C. It is unsuitable because the other teams will need a means to be updated on progress and feedback.
D. It is unsuitable because the daily stand-up is NOT a communication tool or technique.
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 3:Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The Apps and Social Media work package includes the following requirements:
1. Fitness app - Must Have
2. Healthy eating app - Should Have
The burn-down chart is showing an ever-increasing negative gap between the ideal rate of progress and what has actually been delivered. The team manager decided not to deliver the healthy eating app. However, it is still forecast that requirement 1 cannot be completed within the current timebox.
The team manager escalated the issue to the project manager who instructed the team manager to immediately remove the burn-down chart from the information radiator.
What BEST explains how this approach applies the 'manage by exception' principle while taking into account the PRINCE2 Agile behaviours?
A. It applies the principle poorly because everyone in the Website Team should be aware that the work package is outside of tolerance.
B. It applies the principle poorly because the Website Team should be empowered to deal with issues relating to the work package.
C. It applies the principle well because the project manager will now decide how to proceed with the issue.
D. It applies the principle well because the project manager's decision helps the Website Team self- organize within the constraints of the work package.
正解:B
解説: (Topexam メンバーにのみ表示されます)
質問 4:Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team is not sure whether all the information, photos and links needed for the website pages being set up by the Website Team can be delivered within the current timebox.
One of the team members has suggested that the team regularly visit the LGA's cafeteria to show the staff in other departments some rough drawings of the website pages to get their feedback. This can then be used to help decide which parts of each page are most important to deliver within the timebox.
Which BEST explains how this approach manages change?
A. It is a good approach because changes to the website information should be based on feedback.
B. It is a poor approach because some of the website pages should be moved to the next timebox.
C. It is a poor approach because exploration is a behaviour that requires a creative environment to enable change.
D. It is a good approach because changes at the high level for a timebox will NOT affect the baseline.
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 5:Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre oftown has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The following assessment was made initially during the 'starting up a project' process:
'The Website Team is already using Scrum and it is expected that this team will be familiar with agile techniques. However, the Staff Training Team is less familiar with the agile ways of working.' Training on agile techniques was given to the Staff Training Team as a result of this assessment.
As part of the 'closing a project" process, the following observation was made:
'The Staff Training Team gained more understanding of what to fix and what to flex as the project moved into Stage 3.' Why should this observation appear in the end project report?
A. The end project report should review the use of the Agilometer and the agile ways of working.
B. The end project report should sum up the results of each timebox and stage.
C. The end project report should review how much scope was delivered by the project.
D. The end project report should hand over the remaining Could Haves to operational staff.
正解:A
解説: (Topexam メンバーにのみ表示されます)