質問 1:
Which option outlines changes you can make to a simulation plan when evaluating demand and supply?
A. Add demands, cancel demands, reschedule demands, add new planned orders, reschedule supplies
B. Add demands, cancel demands, reschedule demands, add supply, cancel supply, reschedule supplies
C. Change item specification values, change item lead times, change item-organization specification values
D. Change item specification values, change item lead times, create mass changes for items all at once, change item-organization specification values
E. Change item specification values, change item lead times, create mass changes for items
正解:B
質問 2:
The structure of the Plan Summary Layout is a predefined __________.
A. Set of Exceptions
B. Material Plan view
C. Set of Infotiles
D. Group of Reports
E. Supply Demand Workbench
正解:C
質問 3:
Your client has a requirement to restrict Supply Plan data access. Identify three Data Access Set detail entities that can be used to restrict plan data access. (Choose three.)
A. Demand Class
B. Transaction Type
C. Customer
D. Supplier
E. Item
F. Material Planner
正解:C,D,E
解説: (Topexam メンバーにのみ表示されます)
質問 4:
During implementation, the customer would like to use safety stock planning parameters. However, they would like to uncheck "Safety stock change interval to all items." What will the results be if they choose to uncheck this parameter?
A. Safety stock change interval will only apply to items with Days of Cover safety stock method.
B. This option will require a min/max quantity for this parameter even though it will not be used.
C. Safety stock will not be calculated at all for this plan.
D. Safety stock will use a smoothing method to calculate the safety stock within change interval to determine the level of safety stock needed without this parameter.
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 5:
You want to check how many items have excess inventory. Which three choices will get you there? (Choose three.)
A. Open Table, Graph, or Tile Set > Table: Item Exceptions Summary > Filter by Items with Excess Inventory
B. Open Table, Graph, Tile Set > Table: Items > Select any Item > Drill to: Item Exceptions > Expand Supply Planning Exceptions > Select Items with Excess Inventory > Refresh the search results
C. Manage Plans > Edit Plan Options > Select Supply tab > Navigate to Item area > Filter by Items with Excess Inventory
D. Open Table, Graph, or Tile Set > Table: Exceptions > Expand Supply Planning Exceptions > Select Items with Excess Inventory
E. Open Table, Graph, or Tile Set > Table: Items with Exceptions > Filter by Items with Excess Inventory
正解:B,C,D
解説: (Topexam メンバーにのみ表示されます)
質問 6:
Should value in Adjusted Shipments Forecast measure always be equal to the Final Shipments Forecast measure?
A. Yes, if the adjustment is made below the aggregation level at which it is viewed.
B. No, both measures will always be different.
C. Yes,if the adjustment is made at the same aggregation level at which itis viewed, or below.
D. Yes,if the demand plan is approved and values are locked.
E. Yes,if the demand plan hasn't been run again after adjustment.
正解:C
質問 7:
Your client uses product categories and global sourcing rules for supply planning. However, their newest product doesn't follow these rules. For a specific item in the category, it needs to be sourced from a different supplier globally.
How should they set this up for the easiest maintenance, going forward?
A. Create a new global sourcing rule for the item; remove the category level assignments and create new item level assignments for all items in the category pointing each to the correct global sourcing rule.
B. Create a new global sourcing rule for the item; assign it to the assignment set at the item-organization level; alter the category to be category-organization for the remainder of the products.
C. Create a new local sourcing rule for the item; assign it to the assignment set at the item level; leave the category as is for the remainder of the products.
D. Create a new global sourcing rule for the item; assign it to the assignment set at the item-organization level; leave the category as is for the remainder of the products.
E. Create a new global sourcing rule for the item; assign it to the assignment set at the item level; leave the category as is for the remainder of the products.
正解:E
質問 8:
Your client has made a change to item costs. What type of collection do they need to run to only pick up this change?
A. Item costs is automatically updated. No data collection is necessary.
B. Run targeted collection for item costs.
C. Run net change collection for item costs.
D. Item costs cannot be updated via a data collection processes.
E. Must run full data collection. It is not possible to update just item costs.
正解:B
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社の1z0-1066-22問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
TopExamは君に1z0-1066-22の問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。
弊社のOracle 1z0-1066-22を利用すれば試験に合格できます
弊社のOracle 1z0-1066-22は専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社は1z0-1066-22問題集の質問と答えが間違いないのを保証いたします。

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のOracle 1z0-1066-22を利用すれば、君は一回で試験に合格できます。
一年間の無料更新サービスを提供します
君が弊社のOracle 1z0-1066-22をご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたOracle 1z0-1066-22をお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のOracle 1z0-1066-22を持っていることを保証します。
弊社は失敗したら全額で返金することを承諾します
我々は弊社の1z0-1066-22問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のOracle 1z0-1066-22を利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
弊社は無料Oracle 1z0-1066-22サンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料1z0-1066-22サンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこの1z0-1066-22問題集は自分に適するかどうか判断して購入を決めることができます。
1z0-1066-22試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
Oracle 1z0-1066-22 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Create and Manage a Constrained Supply Plan, including Material and Resource Constraints
- Managing Planners, Security and Profile Options
|
トピック 2 | - Configuring UOM, Currency, Disaggregation and Conditional Formatting
- Configuring Pages, Tilesets, Tables and Graphs
|
トピック 3 | - Apply Item Attributes for Supply Planning
- Configure, Run and Manage a Demand Plan
|
トピック 4 | - Managing Sourcing and Approved Suppliers
- Configure Safety Stock Plan options
|
トピック 5 | - Manage Release Recommendations
- Costing and Inventory Foundations
|
トピック 6 | - Integrate S&OP with SCM Cloud and External systems
- Describe Override Demand Forecast and Plan Approval
|
参照:https://education.oracle.com/oracle-planning-and-collaboration-cloud-2022-implementation-professional/pexam_1Z0-1066-22