質問 1:
Given the following User Story: "As an online customer, I would like to be able to cancel the purchase of an individual item from a shopping list so that it only displays the relevant items, in less than 1 second", which of the following can be considered as applicable acceptance test cases?
I.Click on my online shopping list, select the unwanted Item, delete the unwanted item, the unwanted Item is deleted from the shopping list in less than 1 second.
ii.Click on my online shopping list, select all the items, delete all the items, the unwanted items are deleted from the shopping list in less than 1 second.
iii.Tab to the online shopping list and press enter, select the unwanted item, delete the unwanted item, the unwanted item is deleted from the shopping list In less than 1 second.
Iv. Click on the checkout button, select the payment method, make payment, confirmation received of payment and shipping date.
v. Click on my shopping list, select the unwanted Item, delete the unwanted item, the unwanted item is deleted from the shopping list.
Select the correct answer:
A. I, ii and v
B. iv
C. i and iii
D. v
正解:C
質問 2:
From a testing perspective, configuration management
A. Includes all activities that direct and control an organisation with regard to quality
B. Allows the expected results to be compared with the actual results.
C. Focuses on configuring static analysis tools to choose the most suitable breadth and depth of analysis.
D. Allows the tracking of all changes to versions of the testware.
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 3:
Consider the following user story about the authentication functionality of an e-commerce website:
"As a logged-in user, I want to change my current password with a new one, so that I can make my account safer".
The following are some of the acceptance criteria defined for the user story:
[a] After the logged-in user has successfully changed his password, an email confirming the change must be sent to him
[b] To successfully change the password, the logged-in user must enter the current password, enter a new valid password, and finally confirm by pressing the 'Change Password' button
[c] To be valid, the new password entered by the logged-in user is not only required to meet the criteria related to the length and type of characters, but must also be different form the last 5 passwords of that user
[d] A dedicated error message must be presented to the logged-in user when he enters a wrong current password
[e] A dedicated error message must be presented to the logged-in user when he enters the correct current password, but enters an invalid password Based only on the given information, which of the following ATDD tests is most likely to be written first?
A. The logged-in user submits a purchase order containing ten items, selects to pay with a Visa credit card, enters credit card information of a valid card, presses the 'Confirm' button, and finally views the dedicated message confirming that the purchase has been successful
B. The logged-in user enters a wrong current password and views the dedicated error message
C. The logged-in user enters the correct current password, enters an invalid password, and finally views the dedicated error
D. The logged-in user enters the correct current password, enters a valid new password (different from the last 5 passwords), presses the Change Password' button, and finally receives the e-mail confirming that the password has been successfully changed
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 4:
Which one of the following statements correctly describes the term 'debugging'?
A. Debugging is of no relevance in Agile development.
B. Debugging is a confirmation activity that checks whether fixes resolved defects.
C. There is no difference between debugging and testing.
D. Debugging is the development activity that finds, analyses and fixes defects.
正解:D
質問 5:
A test manager decided to skip static testing since he believes bugs can be found easily by doing dynamic testing. Was this decision right or wrong?
A. The decision was wrong. Static testing can find defects early in the development process, reducing the overall cost of testing and development
B. The decision was wrong. Ensuring quality mandates that static testing is performed after performing the dynamic testing.
C. The decision was right. Most of the bugs are easier to identify during the dynamic testing.
D. The decision was right. Static testing is usually redundant if a product is planned to go through a full- cycle of dynamic testing.
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 6:
Which of the following statements about white-box test techniques is true?
A. Branch coverage is the most thorough code-related white-box test technique, and therefore applicable standards prescribe achieving full branch coverage at the highest safety levels for safety-critical systems
B. Achieving full statement coverage and full branch coverage for a software product means that such software product has been fully tested and there are no remaining bugs within the code
C. Code-related white-box test techniques are not required to measure the actual code coverage achieved by black-box testing, as code coverage can be measured using the coverage criteria associated with black-box test techniques
D. Code-related white-box test techniques provide an objective measure of coverage and can be used to complement black-box test techniques to increase confidence in the code
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 7:
In addition to thorough testing of the requirements specification, a development team aims to involve users as early as possible in the development process, using practices such as prototyping, to ensure that the software systems being developed will meet the users' expectations. This approach is especially useful at mitigating the risks associated with one of the seven testing principles, which one?
A. Tests wear out
B. Defects cluster together
C. Absence-of-errors fallacy
D. Working software over comprehensive documentation.
正解:C
解説: (Topexam メンバーにのみ表示されます)
弊社は無料BCS CTFL4サンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料CTFL4サンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのCTFL4問題集は自分に適するかどうか判断して購入を決めることができます。
CTFL4試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
弊社は失敗したら全額で返金することを承諾します
我々は弊社のCTFL4問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のBCS CTFL4を利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のCTFL4問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
TopExamは君にCTFL4の問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。
一年間の無料更新サービスを提供します
君が弊社のBCS CTFL4をご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたBCS CTFL4をお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のBCS CTFL4を持っていることを保証します。
弊社のBCS CTFL4を利用すれば試験に合格できます
弊社のBCS CTFL4は専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はCTFL4問題集の質問と答えが間違いないのを保証いたします。

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のBCS CTFL4を利用すれば、君は一回で試験に合格できます。
BCS CTFL4 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Fundamentals of Testing: It discusses the basic principles related to testing. The topic evaluates your understandings about the test process.
|
トピック 2 | - Managing the Test Activities: This topic explains how to plan tests in general, monitor and control test activities, and report defects in a clear and understandable way.
|
トピック 3 | - Static Testing: The topic covers static testing basics, the feedback and review process.
|
参照:https://www.bcs.org/qualifications-and-certifications/certifications-for-professionals/software-testing-certifications/istqb-certified-tester-foundation-level/