質問 1:
A local council is looking at ways it can fund a large construction project they are planning-the building of a new hospital. Discuss ways in which the council could fund the project, and the advantages and disadvantages of this (25 points)
正解:
See the answer in Explanation below:
Explanation:
A local council, operating in the public sector, has several options to fund a large construction project like a new hospital. Below are three funding methods, with their advantages and disadvantages explained step-by- step:
* Government Grants or Funding
* Step 1: Identify SourceApply for grants from central government or public health budgets allocated for infrastructure.
* Step 2: ProcessSubmit detailed proposals outlining costs, benefits, and public value to secureapproval.
* Advantages:
* No repayment required, preserving council funds.
* Aligns with public sector goals of service delivery.
* Disadvantages:
* Competitive process with uncertain approval.
* Strict conditions may limit flexibility in project execution.
* Public-Private Partnership (PPP)
* Step 1: Establish PartnershipCollaborate with a private firm to finance and build the hospital, with the council leasing it back over time.
* Step 2: ProcessNegotiate terms (e.g., Private Finance Initiative-PFI) where the private partner recovers costs via payments or service contracts.
* Advantages:
* Reduces upfront council expenditure, spreading costs over years.
* Leverages private sector expertise and efficiency.
* Disadvantages:
* Long-term financial commitments increase future budgets.
* Potential loss of control over project specifications.
* Borrowing (e.g., Municipal Bonds or Loans)
* Step 1: Secure FundsIssue bonds to investors or obtain loans from financial institutions, repayable over decades.
* Step 2: ProcessGain approval from government regulators and allocate tax revenues for repayment.
* Advantages:
* Immediate access to large capital for construction.
* Retains council ownership of the hospital.
* Disadvantages:
* Interest payments increase overall project cost.
* Debt burden may strain future budgets.
Exact Extract Explanation:
The CIPS L5M4 Study Guide highlights funding options for public sector projects:
* Government Grants:"Grants provide non-repayable funds but often come with stringent compliance requirements" (CIPS L5M4 Study Guide, Chapter 4, Section 4.4).
* PPP:"Public-private partnerships enable infrastructure development without immediate fiscal pressure, though long-term costs can escalate" (CIPS L5M4 Study Guide, Chapter 4, Section 4.5).
* Borrowing:"Borrowing via bonds or loans is common for public bodies, offering flexibility but adding debt obligations" (CIPS L5M4 Study Guide, Chapter 4, Section 4.2).These align with the public sector' s focus on value for money and service provision. References: CIPS L5M4 Study Guide, Chapter 4:
Sources of Finance.===========
質問 2:
What are three financial risks in exchange rate changes and how might an organization overcome these? (25 points)
正解:
See the answer in Explanation below:
Explanation:
Exchange rate changes pose financial risks to organizations engaged in international trade. Below are three risks and mitigation strategies, explained step-by-step:
* Transaction Risk
* Step 1: Define the RiskLoss from exchange rate fluctuations between invoicing and payment (e.
g., a stronger supplier currency increases costs).
* Step 2: MitigationUse forward contracts to lock in rates at the time of contract agreement.
* Step 3: OutcomeEnsures predictable costs, avoiding cash flow disruptions.
* Translation Risk
* Step 1: Define the RiskImpact on financial statements when converting foreign subsidiary earnings to the home currency (e.g., weaker foreign currency reduces reported profits).
* Step 2: MitigationHedge via currency swaps or maintain natural hedges (e.g., matching foreign assets and liabilities).
* Step 3: OutcomeStabilizes reported earnings, aiding financial planning.
* Economic Risk
* Step 1: Define the RiskLong-term currency shifts affecting competitiveness (e.g., a stronger home currency makes exports pricier).
* Step 2: MitigationDiversify operations or sourcing across countries to spread exposure.
* Step 3: OutcomeReduces reliance on any single currency's performance.
Exact Extract Explanation:
The CIPS L5M4 Study Guide identifies these risks and solutions:
* Transaction Risk:"Arises from timing differences in international payments, mitigated by forwards" (CIPS L5M4 Study Guide, Chapter 5, Section 5.1).
* Translation Risk:"Affects consolidated accounts and can be managed through hedging or balance sheet strategies" (CIPS L5M4 Study Guide, Chapter 5, Section 5.1).
* Economic Risk:"Long-term exposure requires strategic diversification" (CIPS L5M4 Study Guide, Chapter 5, Section 5.1).These align with managing FX volatility in procurement. References: CIPS L5M4 Study Guide, Chapter 5: Managing Foreign Exchange Risks.===========
質問 3:
ABC Ltd wishes to implement a new communication plan with various stakeholders. How could ABC go about doing this? (25 points)
正解:
See the answer in Explanation below:
Explanation:
To implement a new communication plan with stakeholders, ABC Ltd can follow a structured approach to ensure clarity, engagement, and effectiveness. Below is a step-by-step process:
* Identify Stakeholders and Their Needs
* Step 1: Stakeholder MappingUse tools like the Power-Interest Matrix to categorize stakeholders (e.g., employees, suppliers, customers) based on influence and interest.
* Step 2: Assess NeedsDetermine communication preferences (e.g., suppliers may need contract updates, employees may want operational news).
* Outcome:Tailors the plan to specific stakeholder requirements.
* Define Objectives and Key Messages
* Step 1: Set GoalsEstablish clear aims (e.g., improve supplier collaboration, enhance customer trust).
* Step 2: Craft MessagesDevelop concise, relevant messages aligned with objectives (e.g., "We're streamlining procurement for faster delivery").
* Outcome:Ensures consistent, purpose-driven communication.
* Select Communication Channels
* Step 1: Match Channels to StakeholdersChoose appropriate methods: emails for formal updates, meetings for key partners, social media for customers.
* Step 2: Ensure AccessibilityUse multiple platforms (e.g., newsletters, webinars) to reach diverse groups.
* Outcome:Maximizes reach and engagement.
* Implement and Monitor the Plan
* Step 1: Roll OutLaunch the plan with a timeline (e.g., weekly supplier briefings, monthly staff updates).
* Step 2: Gather FeedbackUse surveys or discussions to assess effectiveness and adjust as needed.
* Outcome:Ensures the plan remains relevant and impactful.
Exact Extract Explanation:
The CIPS L5M4 Study Guide emphasizes structured communication planning:
* "Effective communication requires identifying stakeholders, setting clear objectives, selecting appropriate channels, and monitoring outcomes" (CIPS L5M4 Study Guide, Chapter 1, Section 1.8). It stresses tailoring approaches to stakeholder needs and using feedback for refinement, critical for procurement and contract management. References: CIPS L5M4 Study Guide, Chapter 1:
Organizational Objectives and Financial Management.===========
質問 4:
When would a buyer use a 'Strategic Assessment Plan'? Outline how this would work (25 marks)
正解:
See the answer in Explanation below:
Explanation:
A Strategic Assessment Plan (SAP) is a structured framework used by buyers to evaluate and align procurement activities with an organization's long-term goals, ensuring strategic and financial success. In the context of the CIPS L5M4 Advanced Contract and Financial Management study guide, an SAP is a tool to assess suppliers, markets, or contracts strategically, focusing on value creation, risk management, and performance optimization. Below is a detailed explanation of when a buyer would use an SAP and how it works, broken down step-by-step.
Part 1: When Would a Buyer Use a Strategic Assessment Plan? (10 marks)
A buyer would use a Strategic Assessment Plan in scenarios where procurement decisions have significant strategic, financial, or operational implications. Below are key circumstances:
* High-Value or Strategic Contracts:
* When dealing with high-value contracts or strategic suppliers (e.g., critical raw materials), an SAP ensures the supplier aligns with long-term organizational goals.
* Example: Rachel (Question 17) might use an SAP to assess suppliers for a 5-yearraw material contract.
* Complex or Risky Markets:
* In volatile or complex markets (e.g., fluctuating prices, regulatory changes), an SAP helps assess risks and opportunities to inform sourcing strategies.
* Example: XYZ Ltd (Question 7) might use an SAP to navigate the steel market's price volatility.
* Supplier Development or Innovation Goals:
* When aiming to develop suppliers (Question 3) or leverage their innovation capacity (Question
2), an SAP evaluates their potential to contribute to strategic objectives.
* Example: Assessing a supplier's ability to innovate in sustainable materials.
* Long-Term Planning and Alignment:
* During strategic sourcing (Question 11) or industry analysis (Question 14), an SAP aligns procurement with corporate objectives like sustainability or cost leadership.
* Example: Ensuring supplier selection supports a goal of reducing carbon emissions by 20%.
Part 2: Outline How This Would Work (15 marks)
A Strategic Assessment Plan involves a systematic process to evaluate suppliers, markets, or contracts, ensuring alignment with strategic goals. Below is a step-by-step outline of how it works:
* Define Strategic Objectives:
* Identify the organization's long-term goals (e.g., cost reduction, sustainability, innovation) that the procurement activity must support.
* Example: Rachel's goal might be to secure a reliable, cost-effective raw material supply while meeting environmental standards.
* Establish Assessment Criteria:
* Develop criteria based on strategic priorities, such as financial stability, innovation capacity, sustainability, and scalability (Questions 2, 13, 19).
* Example: Criteria might include a supplier's carbon footprint, delivery reliability, and R&D investment.
* Collect and Analyze Data:
* Gather data on suppliers, markets, or contracts using tools like financial analysis (Question 13), industry analysis (Question 14), or supplier scorecards.
* Example: Rachel might analyze a supplier's financial ratios (e.g., Current Ratio) and market trends (e.g., steel price forecasts).
* Evaluate Options Against Criteria:
* Use a weighted scoring system to assess suppliers or contract options, ranking them based on how well they meet strategic criteria.
* Example: A supplier scoring 90/100 on sustainability and reliability might rank higher than one scoring 70/100.
* Develop Recommendations and Strategies:
* Based on the assessment, recommend actions (e.g., supplier selection, contract terms) and strategies (e.g., supplier development, risk mitigation).
* Example: Rachel might recommend a 5-year contract with a supplier offering sustainable materials and include clauses for price reviews.
* Monitor and Review:
* Implement the plan and regularly review outcomes (e.g., via KPIs-Question 1) to ensure alignment with strategic goals, adjusting as needed.
* Example: Rachel tracks the supplier's delivery performance quarterly to ensure it meets the 98% on-time target.
Exact Extract Explanation:
Part 1: When Would a Buyer Use a Strategic Assessment Plan?
The CIPS L5M4 Advanced Contract and Financial Management study guide does not explicitly define a
"Strategic Assessment Plan" as a standalone term but embeds the concept withindiscussions on strategic procurement, supplier evaluation, and contract planning. It describes strategic assessment as a process to
"align procurement with organizational objectives," particularly for "high-value, high-risk, or strategic activities."
* Detailed Scenarios:
* The guide highlights that strategic assessments are crucial for "complex contracts" (e.g., high- value or long-term-Question 17), where misalignment with goals could lead to significant financial or operational risks.
* In "volatile markets," the guide recommends assessing external factors (Question 14) to mitigate risks like price fluctuations or supply disruptions, a key use case for an SAP.
* For "supplier development" (Question 3) or "innovation-focused procurement" (Question 2), the guide suggests evaluating suppliers' strategic fit, which an SAP facilitates.
* L5M4's focus on "strategic sourcing" (Question 11) underscores the need for an SAP to ensure procurement supports broader goals like sustainability or cost leadership.
Part 2: How It Would Work
The study guide provides implicit guidance on strategic assessment through its emphasis on structured evaluation processes in procurement and contract management.
* Steps Explained:
* Define Objectives: The guide stresses that procurement must "support corporate strategy," such as cost efficiency or sustainability, setting the foundation for an SAP.
* Establish Criteria: L5M4 advises using "strategic criteria" (e.g., innovation, sustainability- Question 19) to evaluate suppliers, ensuring alignment with long-term goals.
* Collect Data: The guide recommends using "market analysis" (Question 14) and "financial due diligence" (Question 13) to gather data, ensuring a comprehensive assessment.
* Evaluate Options: Chapter 2 suggests "weighted scoring" to rank suppliers or options, a practical method for SAP evaluation.
* Develop Strategies: The guide emphasizes translating assessments into "actionable strategies," such as contract terms or supplier development plans (Question 3).
* Monitor and Review: L5M4's focus on "performance management" (e.g., KPIs-Question 1) supports ongoing review to ensure strategic alignment.
* Practical Application for Rachel (Question 17):
* Rachel uses an SAP to evaluate raw material suppliers for a 5-year contract. She defines objectives (cost stability, sustainability), sets criteria (delivery reliability, carbon footprint), collects data (supplier financials, market trends), scores suppliers (e.g., Supplier A: 85/100), recommends a contract with price review clauses, and monitors performance via KPIs (e.g., on- time delivery). This ensures the supplier aligns with her manufacturing organization's strategic goals.
* Broader Implications:
* The guide advises that an SAP should be revisited periodically, as market conditions (Question
14) or organizational priorities may shift, requiring adjustments to supplier strategies.
* Financially, an SAP ensures value for money by selecting suppliers who deliver long-term benefits (e.g., innovation, scalability) while minimizing risks (e.g., supplier failure), aligning with L5M4's core principles.
CIPS L5M4 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Understand and apply the concept of strategic sourcing: This section of the exam measures the skills of procurement and supply chain managers and covers the strategic considerations behind sourcing decisions. It includes an assessment of market factors such as industry dynamics, pricing, supplier financials, and ESG concerns. The section explores sourcing options and trade-offs, such as contract types, competition, and supply chain visibility.
|
トピック 2 | - Understand and apply financial techniques that affect supply chains: This section of the exam measures the skills of procurement and supply chain managers and covers financial concepts that impact supply chains. It explores the role of financial management in areas like working capital, project funding, WACC, and investment financing. The section also examines how currency fluctuations affect procurement, including the use of foreign exchange tools like forward contracts and derivative instruments.
|
トピック 3 | - Understand and apply tools and techniques to measure and develop contract performance in procurement and supply: This section of the exam measures the skills of procurement and supply chain managers and covers how to apply tools and key performance indicators (KPIs) to monitor and improve contract performance. It emphasizes the evaluation of metrics like cost, quality, delivery, safety, and ESG elements in supplier relationships. Candidates will explore data sources and analysis methods to improve performance, including innovations, time-to-market measures, and ROI.
|
トピック 4 | - Analyse and apply financial and performance measures that can affect the supply chain: This section of the exam measures the skills of procurement and supply chain managers and covers financial and non-financial metrics used to evaluate supply chain performance. It addresses performance calculations related to cost, time, and customer satisfaction, as well as financial efficiency indicators such as ROCE, IRR, and NPV. The section evaluates how stakeholder feedback influences performance and how feedback mechanisms can shape continuous improvement.
|
参照:https://www.cips.org/qualifications/advanced-diploma-in-procurement-supply/advanced-contract-and-financial-management
弊社のCIPS L5M4を利用すれば試験に合格できます
弊社のCIPS L5M4は専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はL5M4問題集の質問と答えが間違いないのを保証いたします。

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のCIPS L5M4を利用すれば、君は一回で試験に合格できます。
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のL5M4問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
弊社は失敗したら全額で返金することを承諾します
我々は弊社のL5M4問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のCIPS L5M4を利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
一年間の無料更新サービスを提供します
君が弊社のCIPS L5M4をご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたCIPS L5M4をお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のCIPS L5M4を持っていることを保証します。
弊社は無料CIPS L5M4サンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料L5M4サンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのL5M4問題集は自分に適するかどうか判断して購入を決めることができます。
L5M4試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
TopExamは君にL5M4の問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。