HACKER SAFEにより証明されたサイトは、99.9%以上のハッカー犯罪を防ぎます。
カート(0

PMI PMI-SP 問題集

PMI-SP

試験コード:PMI-SP

試験名称:PMI Scheduling Professional

最近更新時間:2026-07-24

問題と解答:全326問

PMI-SP 無料でデモをダウンロード:

PDF版 Demo ソフト版 Demo オンライン版 Demo

追加した商品:"PDF版"
価格: ¥6599 

無料問題集PMI-SP 資格取得

質問 1:
Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?
A. $163,626
B. 0.16
C. -$985,040
D. $130,901
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 2:
You are the project manager for your company. You are working with the activities defined in the figure below.

What will happen to your project if Activity F takes five additional days to complete than what was expected?
A. Your project's critical path will shift to ACFI.
B. Your project will be late by five days.
C. Your project can still complete on time as float is available onActivity I.
D. Your project will now have two critical paths.
正解:B
解説: (Topexam メンバーにのみ表示されます)

質問 3:
You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?
A. 25
B. 300
C. 50
D. 600
正解:B
解説: (Topexam メンバーにのみ表示されます)

質問 4:
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?
A. $122,845
B. -$85,000
C. Zero
D. -$51,000
正解:D
解説: (Topexam メンバーにのみ表示されます)

質問 5:
You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?
A. Schedule variance report
B. Exceptions report
C. Performance management report
D. Cost variance report
正解:B
解説: (Topexam メンバーにのみ表示されます)

質問 6:
Once the project's WBS has been created what process may happen next?
A. Define activities
B. Sequence activities
C. Estimate activity durations
D. Estimate activity resources
正解:A
解説: (Topexam メンバーにのみ表示されます)

質問 7:
Which of the following statements best describes an activity in a project?
A. It is a listing of all project work that must be accomplished for the project scope to be considered complete.
B. It is the effort needed to complete a work package.
C. It is the unit of resource utilization needed to complete a project deliverable.
D. It is a defined set of functions a resource must complete for the project scope to be considered complete.
正解:B
解説: (Topexam メンバーにのみ表示されます)

PMI PMI-SP 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Collect resource information and updates via reports, timesheets, meetings, inspections
  • Develop the project resource breakdown structure (RBS)
トピック 2
  • Perform schedule risk analysis using quantitative tools or techniques
  • Analyze major milestones against statement of work (SOW)
トピック 3
  • Adjust schedule model based upon resource availability
  • Establish the Performance Measurement Baseline (PMB)
トピック 4
  • Perform schedule analysis and audit, on in-house and subcontractor schedules
  • Provide information about project scheduling objectives and goals
トピック 5
  • Establish project schedule configuration management policies and procedures incorporating best practices
  • Align schedule with the overall program plan or integrated master plan (IMP)
トピック 6
  • Obtain a consensus of the project customer, sponsor, project manager
  • Update the schedule model and document schedule baseline changes

参照:http://www.pmi.org/certification/scheduling-professional-sp/pmi-sp-exam-prep.aspx

一年間の無料更新サービスを提供します

君が弊社のPMI PMI-SPをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたPMI PMI-SPをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のPMI PMI-SPを持っていることを保証します。

弊社は無料PMI PMI-SPサンプルを提供します

お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料PMI-SPサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのPMI-SP問題集は自分に適するかどうか判断して購入を決めることができます。

PMI-SP試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。

安全的な支払方式を利用しています

Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のPMI-SP問題集は全部Credit Cardで支払われることができます。

領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。

弊社は失敗したら全額で返金することを承諾します

我々は弊社のPMI-SP問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のPMI PMI-SPを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。

TopExamは君にPMI-SPの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。

弊社のPMI PMI-SPを利用すれば試験に合格できます

弊社のPMI PMI-SPは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はPMI-SP問題集の質問と答えが間違いないのを保証いたします。

PMI-SP無料ダウンロード

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のPMI PMI-SPを利用すれば、君は一回で試験に合格できます。

PMI-SP 関連試験
PMI-CPMAI-JPN - PMI Certified Professional in Managing AI (PMI-CPMAI日本語版)
PMI-PMOCP-JPN - PMI Project Management Office Certified Professional (PMI-PMOCP日本語版)
PgMP - Program Management Professional (PgMP)
DAVSC - Disciplined Agile Value Stream Consultant
PMI-PMOCP - PMI Project Management Office Certified Professional
連絡方法  
 [email protected] サポート

試用版をダウンロード

人気のベンダー
Apple
Avaya
CIW
FileMaker
Lotus
Lpi
OMG
SNIA
Symantec
XML Master
Zend-Technologies
The Open Group
H3C
3COM
ACI
すべてのベンダー
TopExam問題集を選ぶ理由は何でしょうか?
 品質保証TopExamは我々の専門家たちの努力によって、過去の試験のデータが分析されて、数年以来の研究を通して開発されて、多年の研究への整理で、的中率が高くて99%の通過率を保証することができます。
 一年間の無料アップデートTopExamは弊社の商品をご購入になったお客様に一年間の無料更新サービスを提供することができ、行き届いたアフターサービスを提供します。弊社は毎日更新の情況を検査していて、もし商品が更新されたら、お客様に最新版をお送りいたします。お客様はその一年でずっと最新版を持っているのを保証します。
 全額返金弊社の商品に自信を持っているから、失敗したら全額で返金することを保証します。弊社の商品でお客様は試験に合格できると信じていますとはいえ、不幸で試験に失敗する場合には、弊社はお客様の支払ったお金を全額で返金するのを承諾します。(全額返金)
 ご購入の前の試用TopExamは無料なサンプルを提供します。弊社の商品に疑問を持っているなら、無料サンプルを体験することができます。このサンプルの利用を通して、お客様は弊社の商品に自信を持って、安心で試験を準備することができます。