質問 1:You have written a defect report and have just been notified that it is in the "returned" state.
Who should take action on this defect? [1]
A. The project manager who is responsible for the project
B. The developer to whom the defect is assigned
C. The tester who wrote the defect report
D. The defect triage team
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 2:You have directed one of your testers to construct a "smoke test" to execute against new builds prior to starting formal testing. This is an example of which software development lifecycle activity?
[1]
A. Project management
B. Software development and maintenance
C. Change and configuration management
D. Technical support
正解:C
解説: (Topexam メンバーにのみ表示されます)
質問 3:Your test process is fully integrated into the software development lifecycle. You are at which TMMi level?
[1]
A. Defined
B. Managed
C. Optimized
D. Initial
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 4:You are using this skills assessment spreadsheet in order to define a training development plan for your test team.
Your objective is to fill the skill gaps by having at least a team member rated as an expert for each skill identified for the "technical expertise" and "testing skills" sections, and with the ability to train the other team members.
Considering the budget constraints you can send only one person to a training course.

Based only on the given information, which of the following answers would you expect to be the best option to achieve your objective?
Number of correct responses: 1
K43 credits
A. Send Alex to a performance testing training course
B. Send Robert to a performance testing training course
C. Send Mark to a test automation training course
D. Send John to a performance testing training course
正解:A
質問 5:You are the Test Manager for a new product that is being developed according to an iterative lifecycle. At this point, you have 100% of your smoke tests automated, 20% of your functional tests and 50% of your regression tests. Your iterations are four weeks long. You are finding that with each iteration significant maintenance is required for your automated tests and you are not able to complete the testing within the planned timeframe. The test plan you created at the beginning of the project indicates that all automated tests should be run before any manual tests.
Which of the following is a reasonable change to this plan based on how the project is going? [2]
A. Continue to run the automated smoke tests first, execute the automated regression test and new manual functional tests in parallel, and discontinue automating any new functional test cases.
B. Run the automated regression tests first then proceed with the manual and automated functional tests, discontinuing the automated smoke.
C. Run the manual tests first and maintain the automation as time allows.
D. Continue to run all the automation first, performing whatever maintenance is needed and then transfer testing resources from manual testing to increase the automation coverage.
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 6:The Test Manager must assemble team members that have which of the following characteristics? [1]
A. Possess identical skill sets
B. Will spark informal cross training among themselves
C. Thrive in a routine, structured environment
D. Will not change the severity of a defect report
正解:B
解説: (Topexam メンバーにのみ表示されます)
質問 7:Which testing metric identifies defect density? [1]
A. People
B. Project
C. Process
D. Product
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 8:Test Management
You are working on a project to develop an authentication system for an e-commerce website. This system provides two features: Registration and authentication. Two different development teams develop these two features.
There is a high likelihood that the delivery of the authentication feature to the test team will be three weeks later. To complete the registration the user must provide the following registration inputs: Name, surname, birthdate, fiscal code and he/she can select a username and a password.
A registered user can be a special user or a normal user. To be identified as a special user, he/she must also provide, during the registration process, a voucher possibly received from the IT department.
Access is granted only if a user is registered and the password is correct: In all other cases access is denied. If the registered user is a special user and the password is wrong, a special warning is shown on the system console.
You are currently performing a quality risk analysis using FMEA.
Based only on the given information, which of the following is NOT a product risk that could be identified during the quality risk analysis?
Number of correct responses: 1
K43 credits
A. The authentication system denies access for a special user with a wrong password, but doesn't display a special warning on the system console
B. The authentication system grants access to a normal user with a wrong password
C. The authentication system grants access to a special user with a wrong password
D. The late delivery of the authentication feature to the test team causes delays in the start of test execution and this could result in a shorter test period
正解:D
質問 9:While mining the defect database for patterns of problems in the last release, a Test Manager notices that many of the most damaging failures were caused by defects injected during the low-level design phase.
Which of the following actions will likely give this project the most effective solution to this problem? [3]
A. Increased white-box coverage during system testing
B. Formal inspections of the code modules affected by the last release
C. Increased static analysis during the implementation phase
D. Mandatory reviews of all important design work products
正解:D
解説: (Topexam メンバーにのみ表示されます)
ISQI CTAL-TM_Syll2012 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Includes people in roles such as testers test analysts test engineers
|
トピック 2 | - User acceptance testers and software developers
|
トピック 3 | - Advanced Level qualify cation is also appropriate for anyone who wants a deeper understanding of software testing.
|
参照:https://isqi.org/bd/istqb-certified-tester-advanced-level-test-manager#/26-language-german/28-exam-public_exam_session/32-time_extension-no/64-2try_exam-na
一年間の無料更新サービスを提供します
君が弊社のISQI CTAL-TM_Syll2012をご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたISQI CTAL-TM_Syll2012をお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のISQI CTAL-TM_Syll2012を持っていることを保証します。
弊社は無料ISQI CTAL-TM_Syll2012サンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料CTAL-TM_Syll2012サンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのCTAL-TM_Syll2012問題集は自分に適するかどうか判断して購入を決めることができます。
CTAL-TM_Syll2012試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
弊社は失敗したら全額で返金することを承諾します
我々は弊社のCTAL-TM_Syll2012問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のISQI CTAL-TM_Syll2012を利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
弊社のISQI CTAL-TM_Syll2012を利用すれば試験に合格できます
弊社のISQI CTAL-TM_Syll2012は専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はCTAL-TM_Syll2012問題集の質問と答えが間違いないのを保証いたします。

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のISQI CTAL-TM_Syll2012を利用すれば、君は一回で試験に合格できます。
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のCTAL-TM_Syll2012問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
TopExamは君にCTAL-TM_Syll2012の問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。