質問 1:
A project manager is leading a project with a negative risk that has just become an issue. The risk has been recorded, and a response plan has been set. However, a project team member proposes a response that differs from the response recorded in the risk management plan, which the team member believes will be cheaper and equally effective.
What should the project manager do?
A. Ask the project team member to write a formal email explaining the proposal and send it to the change control board (CCB).
B. Adhere to the issue response proposed in the risk management plan, as it is the agreed-upon solution.
C. Evaluate the new proposal with the project team to determine if it is a more beneficial alternative.
D. Implement the new proposal as soon as possible, as it is supposed to be cheaper and equally effective.
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 2:
The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team Which two actions should the project manager take? (Choose two)
A. Review the issue with project sponsor and submit a change request
B. Analyze the business benefits criteria and assumptions
C. Report the issue to the product manager and business segments
D. Schedule a project review meeting to analyze the root cause
E. Discuss the issue with the operations team to assess expense overruns
正解:B,D
解説: (Topexam メンバーにのみ表示されます)

質問 3:
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team ' s knowledge of agile is varied.
The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
A. Ask to execute the project with a predictive approach since there is a budget and schedule risk.
B. Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.
C. Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.
D. Plan for training on agile tools and techniques used in the defined hybrid methodologyfor consistent application by all team members.
正解:D
解説: (Topexam メンバーにのみ表示されます)

質問 4:
A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed.
What should the project manager do to deliver business value to the client?
A. Request to use the management reserve and crash the project schedule.
B. Explain the need to follow the quality assurance (QA) schedule to the customer.
C. Adopt an incremental project delivery approach.
D. Implement an agile project delivery approach.
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 5:
A project manager is leading a project that has a dependency on the client ' s vendor management system for critical requirements. The vendor management team will not derive any benefits from the project. However, the project requires support from the vendor management head.
What should the project manager do next?
A. Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.
B. Review the terms of reference of the steering committee to include the vendor management head.
C. Work with the sponsor on a communications management plan to obtain support from the vendor management head.
D. Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 6:
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?
A. Use retrospectives to better understand the new technology ' s impact on the schedule, map the skill gaps, and adjust the team accordingly.
B. Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.
C. Replace poorly performing team members with more experienced members, setting an example of accountability for the team.
D. Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.
正解:A
解説: (Topexam メンバーにのみ表示されます)

質問 7:
A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.
What should the project manager do first?
A. Develop the resource management plan and ensure adequate training
B. Replace the current project team members
C. Outsource the task to be completed by a specialized vendor.
D. Update the issue log to account for the lack of team member qualifications
正解:A
解説: (Topexam メンバーにのみ表示されます)

質問 8:
A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)
A. Sprint goal
B. Company mission and vision
C. Product backlog
D. Sprint charter
E. Burndown chart
正解:A,C
解説: (Topexam メンバーにのみ表示されます)

質問 9:
A product owner is continuously adding requirements to a project that will significantly impact project delivery. How should the project manager address this?
A. Reprioritize the work and add all new work to the product backlog.
B. Check with the project team about their availability to continue project work.
C. Consult with senior managers on how to address this to ensure the product owner ' s expectations are fully met.
D. Ask the product owner to reprioritize and consider the project done when the highest priorities are delivered.
正解:D

一年間の無料更新サービスを提供します

君が弊社のPMI PMPをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたPMI PMPをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のPMI PMPを持っていることを保証します。

弊社は失敗したら全額で返金することを承諾します

我々は弊社のPMP問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のPMI PMPを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。

弊社のPMI PMPを利用すれば試験に合格できます

弊社のPMI PMPは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はPMP問題集の質問と答えが間違いないのを保証いたします。

PMP無料ダウンロード

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のPMI PMPを利用すれば、君は一回で試験に合格できます。

弊社は無料PMI PMPサンプルを提供します

お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料PMPサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのPMP問題集は自分に適するかどうか判断して購入を決めることができます。

PMP試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。

安全的な支払方式を利用しています

Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のPMP問題集は全部Credit Cardで支払われることができます。

領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。

TopExamは君にPMPの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。

PMI PMP 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Business Environment: It covers aspects related to project compliance, benefits evaluation, and external business changes.
トピック 2
  • People: This topic focuses on managing conflict, leading teams, supporting team performance, empowering team members and stakeholders. Furthermore, it focuses on ensuring adequate training, mentoring stakeholders, and defining team ground rules.
トピック 3
  • Process: This topic emphasizes project execution. It also discusses managing communications, assessing and managing risks, engaging stakeholders, planning and managing budget
  • resources, and planning and managing schedules.

参照:https://www.pmi.org/certifications/project-management-pmp

PMP 関連試験
PMP-KR - Project Management Professional (PMP Korean Version)
PMI-CP-KR - PMI Construction Professional in Built Environment Projects (PMI-CP) (PMI-CP Korean Version)
PMP-JPN - Project Management Professional (PMP日本語版)
PMP-Deutsch - Project Management Professional (PMP Deutsch Version)
PMI-RMP - PMI Risk Management Professional
連絡方法  
 [email protected] サポート

試用版をダウンロード

人気のベンダー
Apple
Avaya
CIW
FileMaker
Lotus
Lpi
OMG
SNIA
Symantec
XML Master
Zend-Technologies
The Open Group
H3C
3COM
ACI
すべてのベンダー
TopExam問題集を選ぶ理由は何でしょうか?
 品質保証TopExamは我々の専門家たちの努力によって、過去の試験のデータが分析されて、数年以来の研究を通して開発されて、多年の研究への整理で、的中率が高くて99%の通過率を保証することができます。
 一年間の無料アップデートTopExamは弊社の商品をご購入になったお客様に一年間の無料更新サービスを提供することができ、行き届いたアフターサービスを提供します。弊社は毎日更新の情況を検査していて、もし商品が更新されたら、お客様に最新版をお送りいたします。お客様はその一年でずっと最新版を持っているのを保証します。
 全額返金弊社の商品に自信を持っているから、失敗したら全額で返金することを保証します。弊社の商品でお客様は試験に合格できると信じていますとはいえ、不幸で試験に失敗する場合には、弊社はお客様の支払ったお金を全額で返金するのを承諾します。(全額返金)
 ご購入の前の試用TopExamは無料なサンプルを提供します。弊社の商品に疑問を持っているなら、無料サンプルを体験することができます。このサンプルの利用を通して、お客様は弊社の商品に自信を持って、安心で試験を準備することができます。